📄 Pkg job-package / scope PDF on file — click the WO number to open it
⏱ LLI Ordered long-lead item on order, not yet delivered (red = due on/after 13 Oct shutdown)
⏱ LLI Ordered long-lead on order, delivery before shutdown
✓ LLI Delivered long-lead item received on site
⚠ MOC … Management-of-Change status (blank/Assessment = unresolved; T-3 gate risk)
FCO Moved to Workscope Field-Change-Order status (approved & folded into scope)
⚑ 6×1u QA flag — N activities carry a placeholder 1.0 labour-unit (data to cleanse). ⚑ shows at ≥5.
🔧 Shop WO has an off-site shop / prefab activity in the schedule
⛔ Active, no P6 SCH = Yes on the Workscope but the WO appears nowhere in P6 — the real schedule gap
○ Not in P6 candidate SCH blank — candidate or other-train scope carried on the Workscope, not counted as active
— no flags on this WO
✎ Quick note click the note cell (+ note) and type — presets offered; saves in this browser and each entry is date-stamped into the WO’s main 💬 comment
⊘ strike asks for a reason and strikes the row through (e.g. scope covered by another WO) — visual only, all counts stay register-true; ↺ removes it
✓ checked tick when the equipment is verified — the "active WOs checked" tile tracks the total (click it to list what’s checked)
Grid columns: WOs = work-order count · Hrs = budgeted labour · Shop = # WOs with a shop/prefab step · QA⚑ = # WOs with ≥5 placeholder activities.
Tiles are clickable filters and combine — select several to AND them (e.g. active scope + not in P6). Each tile shows what its click adds given the tiles already selected; clicking a tile resets any area/class selection so counts always equal the list. When any filter is active a ✕ clear filters button shows above the work-order count. Areas run in plant process order (air in → product out).